Construction Update: MyCiTi system works in the CBD

Start: September 2010

End: August 2011

Scope of works: Construction of dedicated bus lanes and a trunk bus station on the median (island in the middle of the road) opposite Thibault Square on Hans Strijdom Avenue. This entails widening the existing carriageway and median along Hans Strijdom Avenue and will result in the permanent removal of on-street parking bays along Hans Strijdom Avenue.

Contractor: Martin & East

Construction supervision: Arcus Gibb Consulting Engineers

Progress


IRT Inner City Routes

  • Completion: January 2012
  • Trunk: Red, Feeder: Blue